Install a Receptacle Box and Run the Cable
In a regular installation with nonmetallic (NM) cable, 10-3 NM-B (with ground) cable is run from the primary solution panel up to a recessed socket package. The circuit is usually run with insulated (THHN/THWN) wires inside nonmetallic or EMT conduit if the outlet is surface-mounted, such as on a concrete or block wall. The socket might be a unique surface-mount receptacle or might be a standard dryer receptacle set up in a surface-mounted package.
The way you link the cable or cables in to the package will be determined by the installation. The cable is threaded into the box and secured with a cable clamp with NM cable in finished walls. The conduit is secured to the box with a collar and individual conducting wires are snaked through the conduit and into the box in surface-mounted conduit installations.
Result in the Ground Wire Connection during the Outlet
Link the bare copper (or green insulated) ground cable into the ground screw from the outlet. Note: If the socket is installed in a steel electric field, join the circuit ground cable to two grounding pigtails; link one pigtail into the socket’s ground screw, and link one other to your ground screw from the field.
Link the White Neutral Wire in the Outlet
Remove about 3/4 inches of insulation through the white cable in the cable. Link the white wire that is neutral the silver-colored (basic) terminal regarding the socket. Frequently, the text involves placing the bare cable into the basic slot, then securing it by tightening a screw. In certain designs, you may need certainly to loop the cable around a screw terminal before screwing it ardent straight down.
Connect the Two wires that are hot
Upcoming, strip about 3/4 inches of insulation through the red and black colored hot cables. Safe them towards the two terminals that are hot the socket.
Secure the Outlet
Insert the socket in to the field, very carefully tucking the cables set up, then secure it using the mounting screws. Install the socket address dish.
Prepare to set up the Circuit Breaker
Turn fully off the main circuit breaker in the solution panel. Get rid of the panel address to reveal the panel wiring. Find two adjacent empty slots when you look at the solution panel where in fact the breaker that is double-pole fit. Eliminate the slot monitoring of the panel address where this breaker will be situated.
Testing the branch circuits within the panel by having a voltage tester to ensure the charged energy is down. This is accomplished by pressing one probe associated with the tester to a screw terminal regarding the breaker while pressing one other probe into the ground coach club. But understand that the inbound power through the utility solution lines will continue to be real time; usually do not touch either regarding the bus that is hot operating down the straight straight straight straight back of this panel.
Warning
You should hire an electrician to install the circuit breaker if you are not experienced with working inside an electrical service panel, this is the point where. Also in the event that you install the circuit cable, package, and socket, you could have an electrician make the last connections during the solution panel. Service panels pose a lethal danger of surprise due to the fact energy solution cables feeding the panel additionally the terminal lugs they link to in the panel stay live all the time. Shutting from the main circuit breaker doesn’t turn the power off into the solution feed.
Start a punch-out into the part wall surface associated with solution panel, then place the cable through the opening and secure it with a cable clamp. When you are threading the cable in to the panel, be cautious to not permit the cables to clean from the coach pubs. You will require a lot of extra cable; strip away about 18 ins of external coat through the cable.
Strip about 3/4-inch of insulation through the ends of this white, black colored, and wires that are red.
Link the Ground Wire
Link the floor cable through the dryer socket’s circuit cable to your panel’s ground coach club. This requires placing the bare end associated with the cable right into a slot when you look at the ground bus club and tightening the set screw to secure the cable. Carefully fold the wire that is excess organize it across the external side of the panel.
Link the Neutral Wire
Link the white circuit that is neutral by placing the bare copper end associated with the cable in to a slot within the panel’s basic coach club, then tightening the set screw. Carefully fold the wire that is excess tuck it over the side of the service panel.
Link the Hot cables to the Circuit Breaker
Link the red and black colored hot circuit cables towards the two screw terminals regarding the 30-amp, double-pole circuit breaker. For some breakers, this calls for just placing the bare ends associated with the cables to the slots in the breaker and tightening the set screws.
Carefully fold the extra cable and tuck it across the side of the solution panel.
Mount the Circuit Breaker
Fall into line the new breaker therefore the clips fall on the mounting hooks next to the bus bar that is hot. Press the breaker down firmly until it snaps set up. According to the model of your solution panel, placing the breaker are either a pivoting action or a company inwards push to snap the breaker on the bus pubs.
Complete the Installation
Reinstall the panel address. Switch off all of the branch circuit breakers when you look at the panel. Switch on the primary breaker, then turn on each of this branch circuits, one at any given time. This technique stops the unexpected energy rise that does occur in the event that primary breaker is fired up while most of the circuit breakers are triggered.
Testing the Outlet
Make use of voltage tester to validate that the dryer socket is carrying energy.
You’re now prepared to install the appliance that is 4-prong on your dryer and plug it in.